20mph Zone near schools

We have been advised by Surrey Highways that work will start on the traffic calming measures in Dene Road perhaps on 28th October. This will mean the road will be closed to all traffic  from the junction with Grove Road to the junction with Park Lane.

These works are anticipated to be carried out between the hours of 8am and 5pm as soon as possible within the 6 month period of operation of this Temporary Order that commences on 28 October 2019. Advanced warning signs will be displayed and the temporary closure will only operate when the relevant traffic signs are displayed. Access for emergency services, pedestrians; dismounted cyclists and equestrians will be maintained at all times. The vehicular diversion route will be via Grove Road, The Street and Park Lane.

Whilst the notice allows for a 6 month period the actual start date may differ from the above as other emergency work takes priority.

See plan of the proposed traffic calming measures.